Before a press brake is delivered, confirm the supplied configuration, access route, unloading plan, installation requirements, commissioning checks and training responsibilities. Delivery confirms that equipment arrived; it does not by itself establish readiness for production. Use a written checklist with an owner, required evidence and an open-item status for each stage.
This planning guide is for Canadian shops buying a CNC press brake. It complements the manufacturer’s installation instructions and your site procedures; it is not a lifting plan, electrical design or machine operating manual.
1. Confirm the machine and written scope before shipment
Identify the model, configured bending length and force, control, tooling, clamping, backgauge, supports and safeguarding arrangement. Keep the approved quotation and configuration revision with the order. A brochure image does not establish what will arrive.
- Ask for the installation drawing, shipping dimensions and weight, handling instructions, utility requirements and required service clearances for that configuration.
- Separate freight, unloading, rigging, placement, assembly, electrical connection, commissioning, tooling setup, training and follow-up support in the scope.
- Record who supplies each service, who accepts it and which prerequisites affect scheduling. Agree how changes and additional visits are quoted.
- Confirm delivery destination, site contact, receiving hours and readiness dates. An office location is not a stock or delivery-time guarantee.
2. Review the route, floor and utilities with the responsible specialists
Give the handling contractor the actual transport dimensions, weight and manufacturer-approved lifting information. Review the unloading area, doorway openings, route turns, overhead obstructions and final position. Check the route in the units used by the drawings; 25.4 mm equals 1 inch. Include working and service access in the layout, not just the machine footprint.
Have the responsible parties confirm floor and foundation suitability, anchoring and placement requirements using the installation documents. Do not infer a universal slab thickness, forklift capacity or lifting point from another press brake.
For the Canadian installation address, have the electrical contractor verify the actual available supply against the supplied unit’s requirements. Confirm voltage, phase, frequency, current, protection, disconnect and any transformer requirement. Do not assume every shop or machine uses the same voltage. Review any additional utilities listed for the configuration and assign who completes the work.
| Stage | Evidence to collect | Who should confirm |
|---|---|---|
| Machine scope | Approved configuration and itemized service scope | Buyer and supplier |
| Site access and handling | Route review and handling plan based on supplied-machine data | Site lead and handling contractor |
| Floor and utilities | Model-specific installation documents and completed site review | Responsible site specialists |
| Delivery booking | Readiness confirmation, contacts and agreed receiving window | Buyer, carrier and supplier |
| Commissioning appointment | Completed prerequisites and agreed test/acceptance plan | Buyer and commissioning provider |
3. Record the delivery condition and reconcile the shipment
Follow the agreed receiving procedure. Match the machine identification and packing list to the order; record visible condition, missing items and any discrepancy with dated photographs. Keep shipping documents and supplier/carrier communications together. Unpacking and movement should follow the approved handling arrangements.
Acknowledge receipt separately from commissioning acceptance. Agree how unresolved damage, missing tooling or incomplete utilities affect the next appointment before authorizing additional work.
4. Agree commissioning checks and sample parts
Commissioning should follow the selected machine’s instructions and the scope agreed with the provider. Ask what installation checks, functional checks, safeguarding verification, tooling/configuration checks and documentation will be recorded, and who is authorized to perform them. Do not use an acceptance checklist to bypass a failed prerequisite.
Prepare representative part drawings, material specifications, thicknesses, quantities and inspection criteria before the visit. Include the parts that challenge your actual process: a long bend, a short flange or a part needing several repositioning steps, where relevant to the order. Define dimensions and angle tolerances from the drawing rather than a generic internet number.
Record the tooling and program revision used, material identification, measurements and any agreed corrections. Separate a successful demonstration from an unproven production-rate promise. Our sample-bend evaluation guide helps structure the trial; use the daylight, stroke and clearance guide when assessing part access.
5. Finish with an operator handover and an open-item record
Agree the people, shifts, language, machine configuration and tasks covered by training. Record what each participant demonstrated under the approved procedure, what needs more practice and who decides the scope of authorization. Attendance alone does not prove independent readiness.
Keep operating documents, maintenance instructions, program/tool backups where supported, service contacts and the acceptance record accessible to the shop. Assign each open item an owner, due date and release condition. Read the operator handover checklist for the training record.
For hazardous-energy work, use the site’s equipment-specific procedures and trained, authorized personnel. An emergency stop is not a substitute for an energy-isolation procedure. See CCOHS guidance on lockout/tagout.
Download the delivery and commissioning worksheet
The blank CSV records a responsible owner, evidence, status, due date and release condition. It is a planning aid, not a completed inspection or certification.
Download the delivery and commissioning checklist →
For your quotation, send representative drawings, installation postal code, access constraints, expected timing and the services you want included. Use our drawing-based selection guide and equipment financing preparation page if you are also comparing project scope and funding.
Check these out
Shortlist the machine using your drawings, then agree delivery, commissioning and training scope in writing.

HACO OptiForm
Discuss the selected hydraulic configuration, tooling, backgauge and site requirements for your part mix.
Explore machines →
HACO PressMaster
Review the proposed machine and control configuration, representative sample bends and commissioning scope.
Explore machines →
Dener servo-electric press brakes
Compare DDM and DDS options against your parts. Confirm the supplied model, electrical requirements and handover plan.
Explore machines →Product photographs show example configurations. Confirm supplied equipment and included services in the quotation.
Frequently asked questions
Is delivery the same as commissioning?
No. Delivery records receipt of equipment. Commissioning follows the agreed checks and acceptance plan for the installed configuration. Record receipt, commissioning and operator handover separately.
Is installation and operator training included in every press brake quote?
Confirm each service in the written quotation. Freight, unloading, rigging, electrical work, commissioning, tooling setup and training may have separate responsibilities and charges.
What electrical supply does a press brake need in Canada?
Use the requirements for the supplied machine and have the responsible electrical contractor confirm compatibility with the actual site supply. Do not assume one voltage, phase or connection arrangement applies to every machine or Canadian shop.
What should I prepare for commissioning sample bends?
Provide representative drawings, material specifications, approved tooling and inspection criteria. Agree the test scope, measurement method, acceptance decision and treatment of open items before the visit.